UBEROI MOHINDER SINGH AND ASSOCIATES DOON CONSTRUCTION COMPANY Vs. STATE OF HARYANA
LAWS(SC)-1991-2-40
SUPREME COURT OF INDIA (FROM: PUNJAB & HARYANA)
Decided on February 21,1991

Uberoi Mohinder Singh And Associates Doon Construction Company Appellant
VERSUS
STATE OF HARYANA Respondents

JUDGEMENT

- (1.) The above appeal by the grant of special leave and the writ petition raise almost identical disputes, as such they are disposed of by common order. In order to appreciate the controversy we would narrate the facts of the appeal.
(2.) The State of Haryana after coming into force of the Haryana Minerals (Vesting of Rights) Act, 1973 issued a notification under Ss. (1 of S. 3 of the said Act and acquired the right of the minor minerals in respect of village Basantpur within the District of Gurgaon. On 14/09/1976, a gazette notification was published noticing the general public that minor mineral quarries of Gurgaon district will be put to auction on 30/09/1976. The Punjab Minor Mineral Concession Rules, 1964 (hereinafter referred to as 'the Rules') are also applicable to the State of Haryana. Rule 28 provides for the grant of contracts by auction or tender. On 30/09/1976 an auction was held in respect of minor mineral of sand situated in village Basantpur. The bid of the appellant for Rs. 95,500. 00 per annum was declared to be the highest. According to the terms and conditions of the auction the appellant deposited a sum of Rs. 23,875. 00 as advance contract amount and further sum of Rs. 23,875. 00 as security. The contract was to be valid till 31/03/1978 from the date of the execution of the agreement. The highest bid of the appellant was confirmed by the Director of Industries, government of Haryana on 21/12/1976 and the appellant was called upon to approach the Senior District Industries Officer, Faridabad with non-judicial stamp papers worth Rs. 1,432.50 for execution of the agreement. Under Rule 33 the bidder was required to execute the deed of agreement within one month from the date of communication of acceptance of it failing which the bid shall be deemed to have been revoked and the amounts paid under Rule 30 (2 IV or 31 (3 as the case may be shall be forfeited to the government. The communication of the acceptance of the bid was received by the appellant on 8/11/1976. The appellant in the above circumstances supplied the non-judicial stamp papers on 19/11/1976 vide Annx. I and requested the Senior District Industries Officer to make the contract effective from the date the quarry site is handed over to the appellant after obtaining the clearance and no objection from the Flood Control Department as the entire area lay within the protected area. On 3/12/1976 vide Annx. II the non-judicial stamp papers were returned with a direction that the matter may be typed as provided in Form 'l' and then to submit along with other documents. The appellant was also informed that further action will be taken only after the execution of the contract.
(3.) The case of the appellant is that he came to know that some dispute was going on regarding boundary between the States of U. P. and Haryana and the 'dixit Award' had allotted the major portion of the leasehold area of village Basantpur to U. P. The appellant on 8/12/1976 vide Annx. III wrote a letter to the Senior District Industries Officer that the contract be made effective from the date the area washanded over to the appellant after obtaining clearance and no objection certificate from Flood Control Department, and other departments as major portion of the land lay within protected area. The appellant was called upon on 22/12/1976 to sign the contract but the respondents did not deal with any of the objections raised by the appellant. On 7/07/1977 the appellant received the duly executed contract. However, neither the respondents obtained no objection certificate from the Executive Engineer (Flood and Irrigation) Canal Colony, Faridabad nor delivered the possession of the demised area to the appellant. The contract was made effective from 26/05/1977. The appellant vide Annx. IV dated 8/07/1977 returned the agreement again pointing out all the abovementioned facts and requested the Director of Industries to make necessary changes and make the contract effective only from the date of delivery of possession of the demised area after obtaining no objection certificate from the Executive Engineer (Flood Control) in order to enable the appellant to start extraction and removal of sand. The appellant's case further is that the Director of Industries vide Annx. V dated 12/01/1978 informed the appellant that 'dixit Award' had not yet been implemented and work may be started after getting permission from the Executive Engineer (Flood) Division Faridabad. It was further stated that the appellant was bound to pay the contract amount w. e. f. 27/05/1977 i. e. the date of commencement of the contract agreement. The appellant was further called upon to pay a sum of Rs. 23,875. 00 for the period 6/08/197 7/11/1977 and a further sum of Rs. 23,875. 00 for the period November 26, 197 7/02/1978. It may be made clear at this stage that Annx. V is a copy of letter dated 8/08/1977 from the Director of Industries Hayana to M/s Uberoi Mohinder Singh and Associates (appellant) forwarded to the Senior District Industries Officer, Faridabad by endorsement dated 22/12/1977. However, according to the appellant he did not receive such letter on 8/08/1977 but had received the same on 12/01/1978.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.