STATE OF WEST BENGAL Vs. B K MONDAL AND SONS
LAWS(SC)-1961-12-23
SUPREME COURT OF INDIA (FROM: CALCUTTA)
Decided on December 05,1961

STATE OF WEST BENGAL Appellant
VERSUS
B.K.MONDAL Respondents

JUDGEMENT

Gajendragadkar, J. - (1.) This appeal by special leave arises out of a suit filed by the respondent B. K. Mondal and Sons against the appellant the State of West Bengal on the Original Side of the Calcutta High Court claiming a sum of Rs. 19,325/- for works done by it for the appellant. This claim was made out in two ways. It was alleged that the works in question had been done by the respondent in terms of a contract entered into between the parties and as such the appellant was liable to pay the amount due for the said works. In the alternative it was alleged that if the contract in question was invalid then the respondent's claim fell under S. 70 of the Indian Contract Act. The respondent had lawfully done such works not intending to act gratuitously in that behalf and the appellant had enjoyed the benefit thereof.
(2.) The respondents case was that on February 8, 1944, it offered to put up certain temporary storage godowns at Arambagh in the District of Hooghly for the use of the Civil Supplies Department of the State of Bengal and that the said offer was accepted by the said department by a letter dated February 12, 1944. Accordingly the respondent completed the said construction and its bill for Rs. 39,476/- was duly paid in July 1944. Meanwhile, on April 7, 1944, the respondent was requested by the Sub-Divisional Officer, Arambagh, to submit its estimate for the construction of a kutcha road, guard room, office, kitchen and room for clerks at Arambagh for the Department of Civil Supplies. The respondent alleged that the Additional Deputy Director of Civil Supplies visited Arambagh on April 20, 1944 and instructed the respondent to proceed with the construction in accordance with the estimates submitted by it. Accordingly the respondent completed the said constructions and a bill for Rs. 2,322/8/- was submitted in that behalf to the Assistant Director of Civil Supplies on April 27, 1944. Thereafter the Sub-Divisional Officer, Arambagh required the construction of certain storage sheds at Khanakul and the Assistant Director of Civil Supplies wrote to the respondent on April 18, 1944, asking it to proceed with the construction of the said storage sheds. This work also was completed by the respondent in due course and for the said work a bill for Rs. 17,003/- was submitted. In the present suit the respondent claimed that the two bills submitted by it in which the respondent had claimed Rs. 2,322/8/- and Rs. 17,003/- respectively had remained unpaid and that was the basis of the present claim.
(3.) The appellant denied all the material allegations made by the respondent in its plaint. It alleged that the requests in pursuance of which the respondent claims to have made the several constructions were invalid and unauthorised and did not constitute a valid contract binding the appellant under S.175 (3) of the Government of India Act, 1935 (hereafter called the Act). It pleaded that there was no privity of contract between the respondent and itself and it denied its liability for the entire claim. The written statement filed by the appellant was very vague and general in terms and no specific or detailed pleas had been set out by the appellant in its pleading.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.