JUDGEMENT
R.F.NARIMAN,J. -
(1.) This appeal arises out of a certificate issued under Article 133 read with Article 134A of the Constitution of India by the High Court of Delhi in the
impugned judgment dated 04.12.2020. The question raised in this appeal
is whether a learned single Judge's order refusing to condone the
Appellant's delay in filing an application under section 34 of the Arbitration
and Conciliation Act, 1996 ("Arbitration Act, 1996") is an appealable
order under section 37(1)(c) of the said Act. After considering, in particular,
two judgments of this Court, the High Court held:
"18. We have considered the rival contentions. Though, as observed by us in the hearing on 5th November, 2020, in view of BGS SGS Soma JV supra having referred to the grounds under Section 34 in entirety and not confined to Section 34(2) only, we were inclined to differentiate between a case of return of an application under Section 34 on the ground of the Court to which it is presented not having territorial jurisdiction, on the one hand and rejection of an application under Section 34 on the ground of having not been filed within the prescribed time, on the other hand, but in view of the Supreme Court having been approached against Ramdas Construction Co. supra, expressly holding an appeal as the one before us, to be not maintainable under Section 37, and having dismissed the appeal with a speaking order, though not expressing any opinion on the maintainability of the appeal, we consider ourselves bound thereby and hold this appeal to be not maintainable.
19. We may however observe that Section 37(1)(b) also, while providing for the appealable orders, refers to Section 34 in entirety and not to Section 34(2); though BGS SGS Soma JV supra has held that the order which is appealable thereunder is an order testing the arbitral award on the grounds set out in Section 34 but in our humble opinion if the intention of the legislature was to confine the appeals only to grounds under Section 34(2), nothing prevented them from, instead of referring to Section 34 generally in Section 37(1)(c), referring only to Section 34(2). We are of the view that sub-section (3) of Section 34, by use of the words "˜but not thereafter', as interpreted in Union of India Vs. Popular Construction Co. (2001) 8 SCC 470, restricts the power otherwise vested in Court to condone the delay beyond thirty days, the same also creates a ground of time bar for refusing to set aside the award and is part of the self-contained code for setting aside of the award; thus, refusal to set aside an award on the ground of the said time bar, would be a refusal within the meaning of Section 37 and appealable under Section 37. There is also merit in the contention of Mr. Rajshekhar Rao, Advocate for the appellant that refusal to condone the delay also entails affirmation of the underlying order. Mention in this regard may be made of Section 27 of the Limitation Act, 1963 which, though in the context of suit for possession of any property, extinguishes the right to property at the determination of the period prescribed for instituting the suit for possession thereof. However we need not discuss further since, as aforesaid, we are bound by the dicta in BGS SGS Soma JV and Ramdas Construction Co. supra.
20. We may also consider another aspect. By reading Section 37 as not permitting an appeal against refusal to condone the delay in applying for setting aside of the award, the persons aggrieved by the award are left with no remedy but to approach the Supreme Court by way of a petition under Article 136 of the Constitution of India. The refusal to set aside the award may not necessarily be by the Commercial Division of the High Court but may also be by the Commercial Courts of the country. No other remedy would be available to the persons aggrieved by the award, against the decision of any Commercial Court in the country refusing to condone the delay in applying for setting aside of the award, leaving such persons either with the option of accepting / remaining bound by the award even if having excellent grounds for setting aside of the same or of approaching the Supreme Court under Article 136 of the Constitution of India, thereby putting an avoidable burden on the Supreme Court which, as per the scheme of the Constitution of India, was envisaged to hear limited number of matters entailing constitutional issues and not to hear matters of condonation of delay. Though undoubtedly the scheme of expediency and limited judicial intervention is ingrained in the Arbitration Act but at the same time it cannot be forgotten that the Act nevertheless provides remedies against the arbitral award and it is felt that to vest the order, of any Commercial Court in the country refusing to condone the delay in applying for setting aside of the award, and which delay can be for varying reasons as diverse as the social, geographical and economic conditions prevalent in this country, and not even providing any opportunity to the High Courts to have a look therein, would be a very harsh outcome.
21. Thus, while dismissing the appeal as not maintainable, being bound by the dicta of the Supreme Court in BGS SGS Soma JV and in Ramdas Construction Co. supra, we grant certificate under Article 133 read with Article 134A of the Constitution of India to the appellant."
(2.) It may be noted that the learned single Judge of the High Court dismissed the application for condonation of delay in an application filed under
section 34 of the Arbitration Act, 1996 to set aside an award dated
03.05.2019 vide its judgment dated 04.06.2020, and consequently dismissed the section 34 application itself.
(3.) Shri Rajshekhar Rao, learned Advocate appearing on behalf of the Appellant, has relied strongly upon the judgment of this Court in Essar Constructions v. N.P. Rama Krishna Reddy (2000) 6 SCC 94, which
was a judgment delivered under section 39 of the Arbitration Act, 1940.
His argument is that since section 39 of the 1940 Act is in pari materia with
section 37 of the Arbitration Act, 1996, in that an appeal lies where a single
Judge refuses to condone delay, resulting in an order refusing to set aside
an arbitral award, the ratio of Essar Constructions (supra) would apply
on all fours to the same provision contained in section 37. This being so,
he argued that it is clear that refusal to condone delay would result in a
refusal to set aside an award, an appeal against such order being
maintainable under section 37 of the Arbitration Act, 1996. He also
strongly relied upon the judgments of this Court in Chief Engineer of BPDP/REO Ranchi v. Scoot Wilson Kirpatrick India (P.) Ltd. (2006) 13 SCC 622 and Fuerst Day Lawson Ltd. v. Jindal Exports Ltd. (2011) 8 SCC 333 to buttress his submission that section 39 of the 1940 Act was a
pari materia provision to section 37 of the Arbitration Act, 1996. He then
relied upon judgments of the Madhya Pradesh, Bisleri International Pvt. Ltd. and Ors. v. Sun Petpack Jabalpur Pvt. Ltd. and
Anr. 2009 (4) M.P.L.J. 514. , Bombay, E-Square Leisure Pvt. Ltd., Pune v. K.K. Dani Consultants and Engineers Pvt.
Ltd. 2013 (3) Mh.L.J. 24; Jayshri Ginning & Spinning Pvt. Ltd. v. C.A. Galiakotwala & Company Pvt. Ltd. 2016 SCC OnLine Bom 5067.
, Karnataka, M/s Crompton Greaves Ltd. v. M/s Annapurna Electronics and Ors. ILR 2015 KAR 4199., Delhi, Harmanprit Singh Sidhu v. Arcadia Shares & Stock Brokers Pvt. Ltd. (2016) 234 DLT 30 and Calcutta, Damodar Valley Corporation v. Sanjay Singh Rathor 2018 SCC OnLine Cal 4014. . High Courts to argue that an order refusing to condone delay stands on a completely different footing from an order
which condones delay, as the latter order cannot be said to impart any
finality to the proceeding, as, when an order condones delay, it cannot be
said that the court has refused to set aside an award as it may ultimately
set aside the aforesaid award on the grounds mentioned in section 34(2)
of the Arbitration Act, 1996. He further argued that the judgment of the
Allahabad High Court in Union of India v. Radha Krishna Seth and Anr.,
2005 SCC OnLine All 8400 and that of the Bombay High Court in State of Maharashtra v. Ramdas Construction Co. 2006 (6) Mah. L.J. 678 did
not state the law correctly and ought to be overruled by this Court. He
argued that where a right of appeal is granted by statute, a dismissal on a
preliminary ground is nevertheless a dismissal of the appeal, since it
cannot be heard thereafter. He also argued that a right of appeal, once
granted, ought not to be limited by statutory interpretation where the words
used are capable of a wider construction. In particular, referring to the
language of section 37(1)(c) of the Arbitration Act, 1996, he argued that
there must be refusal to set aside an arbitral award "under section 34",
which includes section 34(3), under which a court may refuse to condone
delay in filing an application under section 34. Coming to the two Supreme
Court judgments referred to in the impugned judgment, it was his
contention that the focus of this Court in BGS SGS Soma JV. v. NHPC
Limited (2020) 4 SCC 234, was on a completely different question,
namely, as to whether an application to set aside an award under section
34 should be returned to the proper court dependent upon where the seat of arbitration was located. It was only in the course of discussion relatable
to this question that this Court approved certain observations made in the
decision of the Delhi High Court in Harmanprit Singh Sidhu v. Arcadia
Shares and Stock Brokers Pvt. Ltd. 2016 SCC OnLine Del 5383, in
which a learned single Judge of the Delhi High Court allowed an
application for condonation of delay, a Division Bench then holding that an
appeal against such an order was not maintainable under section 37 of
the Arbitration Act, 1996. He contended that it is only in this context that
paragraph 17 of BGS SGS Soma (supra) approved of the observations
made in Harmanprit Singh Sidhu (supra), inasmuch as it cannot be said
that the Court has refused to set aside the award under section 34, as it
may yet do so if any of the grounds contained in section 34(2) are made
out. So far as this Court's order dated 12.04.2017 in State of Maharashtra
and Anr. v. M/s Ramdas Construction Co. and Anr. [C.A. Nos. 5247-
5248 of 2007] is concerned, he argued that this Court did not go into the maintainability aspect at all, but ultimately dismissed the Civil Appeals on
the ground that the District Judge, Nagpur had held that the period of delay
being beyond four months, the court had no jurisdiction to entertain the
application for condonation of delay or the application on merits under
section 34 of the Arbitration Act, 1996.;