JUDGEMENT
-
(1.) Leave granted.
(2.) Under an agreement dated 4.11.1992, the appellant (State of Goa) entrusted a construction work (Farm Development Works in Command Area of Water Course No.3 and 3A of minor M-3 of SIP in Salcette Taluka) to the respondent. Clause 25 of the agreement provided for settlement of disputes by arbitration, relevant portions of which are extracted below:
"Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the specifications, designs, drawings and instructions herein before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim right matter or thing whatsoever, in any way arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions orders or these conditions or otherwise concerning the works, or the execution or failure to execute the same whether arising during the progress of the work or after the completion or abandonment thereof shall be referred to the sole arbitration of the person appointed by the Chief Engineer, Central Public Works Department in charge of the work at the time of dispute...................It is a term of contract that the party invoking arbitrations shall specify the dispute or disputes to be referred to arbitration under this clause together with the amount or amounts claimed in respect of each such disputes."
As per the contract, the work had to be commenced on 16.11.1992 and completed by 5.5.1994. On the ground that the contractor did not complete the work even by the extended date of completion (31.3.1995), the contract was terminated by the appellant.
(3.) Respondent raised certain claims and gave a notice to the appellant to appoint an arbitrator in terms of the arbitration clause. As the appellant did not do so, the respondent filed an application under section 11 of the Arbitration and Conciliation Act, 1996 ('Act' of'new Act' for short) for appointment of an arbitrator. By order dated 4.12.1998 the said application was allowed and Mr. S.V.Salilkar, retired Adviser, Konkan Railway Corporation was appointed as the sole arbitrator. The arbitrator entered upon the reference on 22.2.1999 and called upon the parties to file their statement.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.