JUDGEMENT
-
(1.) The respondents, though served, has remained
unrepresented. Leave granted. Heard learned counsel for the
appellant.
(2.) The appellant runs a hospital at Kaithal and is a
consumer of electricity. His premises was inspected by the SDOs
attached to the office of Assistant Director (Vigilance) of
UHBVNL on 4.7.2002. The checking report dated 4.7.2002 issued
in regard to the said inspection recorded that all the M&T
seals were found tampered, that is, lace wire was cut and
reinserted into seal hole and pressed. The meter was removed,
packed in a cardboard box, sealed and delivered to Bhawani
Prasad-AFM. In pursuance of it, a penalty/backbilling notice
dated 5.7.2002 was issued claiming Rs.2,72,677/- as penalty
being the electricity charges assessed for the period of
preceding six months. The appellant was required to deposit the
entire amount to avoid disconnection/to secure restoration of
supply. The appellant therefore deposited the said amount,
under protest on 6.7.2002 and filed an appeal before the
Superintending Engineer against the demand notice. No action
was taken on the said appeal.
(3.) In this background, the appellant filed a suit on
19.9.2002 seeking a declaration that the demand notice dated
5.7.2002 was null and void and for refund of the sum of
Rs.2,72,677/- deposited by him. The suit was contested by the
respondents. The appellant had examined himself as PW.2 and had
examined a clerk of UHBVNL (first defendant) as PW.1 and marked
Ex.P.1 to P.25. The respondents examined the two inspecting
officers as DW.1 and DW.2 and relied upon the checking report
(Ex.D.1) and the demand notice (Ex.D.2). The suit was dismissed
by judgment and decree dated 17.7.2006. The appeal filed by the
appellant was allowed by the Additional District Judge, Kaithal
by judgment and decree dated 11.4.2007. After considering the
evidence in detail, the first appellate Court recorded the
following findings of fact:
(a) That the appellant's premises and installation was
checked by the officers of defendants on 19.2.2002 and all the
M&T seals were found to be in tact and the meter was also found
to be in working condition. Therefore the assumption that there
was theft of electricity for six months preceding the date of
inspection (4.7.2002) was not correct.
(b) There was nothing to show that subsequent to 19.2.2002,
the appellant had tampered with the meter or committed any
theft of electrical energy.
(c) On 4.7.2002, there was an inspection and M&T seals were
found to have been tampered. The meter was dismantled and
removed, but was not tested in any laboratory to show its
functioning was tempered.
(d) DW.1 admitted that he was not in a position to say
whether the meter was slow when it was checked on 4.7.2002. The
finding that M&T seals were tampered was not proof of tampering
of functioning of the meter. There was no averment or proof
that the functioning of the meter was tampered. The earlier
checking on 19.2.2002 was carried out on a complaint dated
18.2.2002 by appellant, about the wrong recording of
consumption by the Meter Reader resulting in Rs.6616/- being
found to be refundable. As a consequence, the Meter Reader was
transferred. The Meter Reader developed a grudge against the
appellant and the employees of the respondents were inimical
towards the appellant; and that in order to settle scores, the
M&T seals were tampered and thereafter the matter reported to
the Vigilance so that there can be inspection and harassment to
the appellant. The entire episode was intended to teach a
lesson to appellant, because he dared to give a complaint
against Meter Reader.
(e) Both the defence witnesses admitted that before issuing
the demand notice, the consumption for the previous months was
not checked and there was no calculation sheet showing how
Rs.2,72,677/- was arrived at.
On these and other findings, the appellate Court held that the
demand for Rs.2,72,677/- was not legal or justified and set
aside the imposition.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.