JUDGEMENT
-
(1.) Both these appeals have been preferred by the rival parties
against the judgment and order dated 24.4.2007 passed by the High
Court of Rajasthan (Jaipur Bench) in Civil Misc. Appeal No.1581 of
2006 under Section 37(1)(A) of the Arbitration and Conciliation Act,
1996 (hereinafter called "Act 1996") against the order dated
17.1.2006 passed by the District Judge, Jaipur City, Jaipur in
Arbitration Case No.89/2004 whereby the application filed by the
State of Rajasthan under Section 34 of the Act 1996 for setting aside
the arbitral award dated 1.12.2003 had been allowed.
(2.) Facts and circumstances giving rise to these appeals are:
A. The Public Works Department of the State of Rajasthan
(hereinafter called "PWD") decided in September 1997 to construct
the Bharatpur bye-pass for the road from Bharatpur to Mathura,
which passed through a busy market of the city of Bharatpur. For the
aforesaid work, tenders were invited with a stipulation that the work
would be executed on the basis of Build Operate and Transfer
(BOT). The total extent of the road had been 10.850 k.ms. out of
which 9.6 k.ms. was new construction and 1.25 k.ms. was
improvement, i.e. widening and strengthening of the existing portion
of Bharatpur-Deeg Road.
B. After having pre-bid conference/meeting and completing the
required formalities it was agreed between the tenderers and PWD
that compensation would be worked out on the basis of investment
made by the concerned entrepreneur. The tender submitted by
MSK-appellant for Rs.1,325 lacs was accepted vide letter dated
5.2.1998 and the MSK-appellant was called upon to furnish security
deposit which was done on 25.7.1998. Concession agreement dated
19.8.1998 was entered into between the parties authorising collection
of toll fee by MSK-appellant. According to this agreement, period of
concession had been 111 months including the period of
construction. The said period would end on 6.4.2008. It also
contained the provisions for making repayment/collection of toll fee
and in case of any difference/dispute to refer the matter to the
Arbitrator.
C. MSK-appellant completed the Bharatpur bye-pass Project on
10.4.2000 and also started collection of toll fee as provided under the
agreement with effect from 28.4.2000. There had been some
problem in collecting the toll fee because of agitation by local
people. The State issued Notification dated 1.9.2000 under the
provisions of the Indian Tolls Act, 1851 and Rajasthan Motor
Vehicles Taxation (Amendment) Act, 1994 (hereinafter called the
'Notification dated 1.9.2000') preventing the entry of vehicles into
Bharatpur city stipulating its operation with effect from 1.10.2000.
MSK-appellant invoked arbitration clause raising the dispute with
respect to:
(a) Delay in issuance of Notification prohibiting entry of
commercial vehicles into Bharatpur town and diverting
traffic through the bye-pass; and
(b) Collection of toll from vehicles using Bharatpur-Deeg patch of
the road.
D. The State/PWD failed to make appointment of the Arbitrator.
MSK-appellant preferred SB Civil Arbitration Application No.31 of
2002 before the High Court and the High Court vide order 12.4.2002
appointed the Arbitrator. The Arbitrators so appointed in their
meeting on 8.5.2002 appointed the third Arbitrator. Claim Petition
was filed before the Tribunal by MSK-appellant on 23.9.2002. The
State submitted its reply to the claim petition on 7.12.2002.
E. The Arbitral Award was made in favour of MSK-appellant on
1.12.2003 according to which there had been delay on the part of the
State of Rajasthan in issuing the Notification and the State failed to
implement the same and the contractor was entitled to collect toll fee
even from the vehicles using Bharatpur-Deeg part of the road . The
State of Rajasthan was directed to pay a sum of Rs.990.52 lacs to
MSK-appellant as loss due upto 31.12.2003 with 18% interest from
31.12.2003 onwards. The Tribunal further gave various other
directions to the State in this regard.
F. Being aggrieved, the State of Rajasthan filed objections under
Section 34 of the Act 1996 and while deciding the same, the District
Judge vide order dated 17.1.2006 set aside the Arbitral Award on the
grounds that there was no clause in the agreement to issue
notification barring the entry of vehicles in the city of Bharatpur; and
the Tribunal erred in taking 1997 survey as basis for calculating the
loss suffered by MSK-appellant. It held that MSK-appellant was not
entitled to any monetary compensation under clause 10 of the
concession agreement, but only entitled to extension of concession
period, and the rate of interest was reduced from 18% to 10%.
G. Being aggrieved, MSK-appellant preferred an appeal before
the High Court wherein the High Court vide impugned judgment and
order dated 24.4.2007 held that Bharatpur-Deeg section was part of
the project and the contractor could collect the toll fee from the users
of this part of the road also. Clause 10 of the concession agreement
was not attracted in the facts of the case. There was no agreement
for issuance of Notification by the State barring the use of old route
and directing the vehicles to use the new route alone. Therefore, the
question of grant of compensation on that account for the traffic loss
could not arise. The District Judge was justified in reducing the rate
of interest from 18% to 10% in view of the provisions of Section
31(7)(b) of the Act,1996 and economic realities, whereby the rate of
interest had been reduced by the Banks in India.
Hence, these two appeals.
(3.) Mr. K.K. Venugopal, learned senior counsel appearing for the
private appellant, has submitted that it was implied in the agreement
and there has been an understanding between the parties that State
Government would issue notification barring the vehicles driven
through the markets of Bharatpur City. This was not even an issue
before the Tribunal and thus, could not be agitated by the State at all.
Thus, the courts below erred in setting aside the award of arbitral
tribunal to that extent, and secondly, that the rate of interest as
reduced from 18 per cent to 10 per cent by the District Court as well
as the High Court is in contravention of the terms of contract between
the parties which fixed the rate of interest at 20 per cent. Further
opposing the appeal by the State of Rajasthan, Shri Venugopal has
submitted that Bharatpur-Deeg patch was an integral part of the
project as there was only one composite contract of the entire bye-
pass and, therefore, the private appellant was entitled to collect the toll
fee from the users of that part of the road also.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.