SUTLAJ CONSTRUCTION COMPANY PRIVATE LIMITED Vs. STATE OF PUNJAB
LAWS(SC)-2001-4-179
SUPREME COURT OF INDIA (FROM: PUNJAB & HARYANA)
Decided on April 17,2001

SUTLEJ CONSTRUCTION COMPANY PRIVATE LIMITED Appellant
VERSUS
STATE OF PUNJAB Respondents

JUDGEMENT

- (1.) Leave granted.
(2.) This appeal is directed against the Impugned judgment of the High Court interfering with an order passed by the Appellate Court in exercise of jurisdiction under Section 115 of the Code of Civil Procedure arising out of an arbitration proceeding. The appellant had entered into an agreement with the State of punjab for certain construction project and dispute having been arisen, in accordance with the arbitration clause, the dispute was referred to the Arbitrator. The Arbitrator case to hold that the contract in question not having been rescinded, the State was not entitled to forfeit the security deposit as well as to retain the equipment and materials belonging to the appellant and on that score awarded certain damages. Against the said award the State filed as objection under sections 30/33 of the Arbitration Act and the contractor filed an application for making the award rule of the Court. The Civil Court on consideration of the entire materials rejected the objection filed by the State and. made the award a rule of the Court. The State went up in appeal against the same under Section 39 and the appeal having failed, the State carried the matter in revision to the High Court. The high Court by the impugned judgment set aside the award as well as the orders passed by the civil Court on interpreting Clauses 45 and 46 of the agreement and came to the conclusion that the Arbitrator committed gross misconduct in awarding the damages on a misconstruction of the relevant clauses of the contract by the High Court.
(3.) Mr. Sachhar, learned senior counsel appearing for the appellant contends that under section 115 of the Code of Civil Procedure the Court was entitled to correct only jurisdictional error and in the absence of any jurisdictional error, the Court exceeded in passing the impugned judgment by re-appreciating the facts. On merits also Mr. Sachhar contended that the High Court committed serious error by misconstruing clause 45 of the agreement in question inasmuch as until and unless a contract is rescinded, the State Government cannot exercise any lien over the instruments and materials belonging to the appellant and in forfeiting the security and in awarding damages.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.