EXECUTIVE ENGINEER DHENKANAL MINOR IRRIGATION DIVISION ORISSA Vs. N C BUDHARAJ
LAWS(SC)-2001-1-44
SUPREME COURT OF INDIA
Decided on January 10,2001

EXECUTIVE ENGINEER,DHENKANAL MINOR IRRIGATION DIVISION,ORISSA Appellant
VERSUS
N.C.BUDHARAJ Respondents

JUDGEMENT

- (1.) I have gone through the two judgments of two of my Brother Judges, on the question of the jurisdiction of the arbitrator to grant interest for the period prior to the reference. While Brother Justice Raju has come to the conclusion that the arbitrator does possess the said power, Brother Justice Mohapatra, has taken a contrary view. Having considered both the view points, I have not been able to persuade myself to agree with the conclusion of Brother Raju, J, and I entirely agree with the conclusion of Brother Mohapatra, J. But in view of the importance of the point, I am tempted to indicate my views in few paragraphs.
(2.) The power of the arbitrator to award interest for the period prior to entertaining upon the reference as well as the period the reference was pending before him pendente lite was considered by this Court in Thawardas, (1955) 2 SCR 48 : (AIR 1955 SC 468) and also by the Privy Council in Bengal Nagpur Railway Co. Ltd. v. Ruttanji Ramji, (1938) 65 Ind App 66 : (AIR 1938 PC 67). Between 1960 and 1972 in several decisions, which have been referred to by the Constitution Bench in G.C.Roy's case, (1992) 1 SCC 508 : (1992 AIR SCW 389 : AIR 1992 SC 732), the question of power of the arbitrator to award interest has been considered but without any detailed discussion, it has been held that the arbitrator possesses the power since the reference to arbitrator was made by the Court and all the disputes in the suit stood referred. This Court, therefore, came to the conclusion that on the application of the principle of Section 34 of the Civil Procedure Code, pendente lite interest could be awarded by the arbitrator. But so far as the power to award interest for the period prior to the reference is concerned, only in the case of Ashok Construction Co., (1971) 3 SCR 66, this Court no doubt held that the arbitrator has the power to award interest from the date the amount is due under the contract, on the ground that the arbitrator agreement did not exclude the jurisdiction of the arbitrator but the earlier decision of the Court either in Thawardas or in Bengal Nagpur Railway, deciding to the contrary, had not been noticed and in fact the question had been disposed of in one sentence in paragraph (6). While this was the position, for the first time, this Court made an indepth examination of the question in Jena's case, (1988) 1 SCC 418 : (AIR 1988 SC 1520). Three learned Judges considered the competence of the arbitrator on reference made without intervention of the Court and came to the conclusion that in cases, which arose prior to the commencement of the Interest Act, 1978, the arbitrator did not have the power to grant interest either pendente lite or for the period prior to the reference. In this case, though several English cases have been cited, including the case of Chandris (1951 (1) KB 240), but the Court refrained from referring, in view of the abundance of authoritative pronouncement of the Supreme Court. Since the Interest Act of 1839 did not confer power on the arbitrator to award interest, the Court looked elsewhere for that power of the arbitrator to award interest up to the institution of the proceeding but could not find any such power, and, therefore, ultimately came to the conclusion that the arbitrator did not possess any power to award interest for the pre-reference period. So far as the power of arbitrator to grant interest pendente lite is concerned, the Court held that Section 34 of the Civil Procedure Code could be made applicable to arbitrations in suit and, therefore, when a dispute is referred to arbitrator in suit, the arbitrator will have the power of the Court in deciding the dispute, but not otherwise. In other words, in case of an arbitration proceeding, where a reference is made to the arbitrator, not by the Court in a pending suit, but otherwise, in accordance with the arbitration clause in agreement, then the arbitrator also did not possess the power to award pendente lite interest as the arbitrator cannot be held to be a Court. It is necessary to bear in mind, it was held in no uncertain terms that there is no substantive law which can be said to have conferred power on the arbitrator to award interest, before the commencement of the proceedings, that is for the pre-reference period. This decision of the three Judge Bench, operated the field till the Constitution Bench decision in G. C. Roy's case (1992) 1 SCC 508 : (1992 AIR SCW 389 : AIR 1992 SC 732). The Constitution Bench overruled the conclusion in Jena's case, so far as it related to the power of the arbitrator pendente lite is concerned. Even in G. C. Roy's case, the Constitution Bench, itself held that the earlier decisions of the Court in Rallia Ram, (1964) 3 SCR 164 : (AIR 1963 SC 1685), Bengal Nagpur Railway, (1938) 65 Ind App 66 : (AIR 1938 PC 67) and Thawardas, (1955) 2 SCR 48 : (AIR 1955 SC 468), what was held in relation to the power of the arbitrator to award interest for pre-reference period is because of the fact, as a matter of substantive law, no such power was available and as such, the ratio in that case cannot have any relevance on the question of arbitrator's power to award interest pendente lite. The Constitution Bench did record a finding that interest pendente lite is not a matter of substantive law, like interest for the period anterior to reference. The Constitution Bench also very carefully expressed - "Untill Jena's case, almost all the Courts in the country had upheld the power of the arbitrator to award interest pendente lite." Even when the earlier Constitution Bench decision in the case of Union of India v. West Punjab Factories Ltd., (1966) 1 SCR 580 : (AIR 1966 SC 395), approving Thawardas, Bengal Nagpur Railway Co. and Rallia Ram, was brought to the notice of the Court, it was observed that not only the said case was not a case under Arbitration Act but also it approved Thawardas only so far as the power to grant interest prior to the institution of the suit and not so far as the power to award interest pendente lite is concerned. If the Constitution Bench in the case of Union of India v. West Punjab Factories Ltd., approved Thawardas, Bengal Nagpur Railway and Rallia Ram and held that even in a suit, interest prior to the institution of the suit cannot be granted, following the principles in Thawardas and two others, which decided the power of the arbitrator in relation to the grant of interest for pre-reference period, it is unimaginable on my part to think that an arbitrator does possess the power on the ground that otherwise it would lead to multiplicity of proceedings. It would be appropriate for me to indicate that in G. C. Roy, the ratio of Thawardas, Bengal Nagpur Railway and Rallia Ram had not been doubted even, and possibly could not have been doubted in view of its acceptance by the earlier Constitution Bench decision in Union of India v. West Punjab Factories Ltd., so far as the power of award of interest for the pre-reference period is concerned. Even subsequent to Roy's case, there have been decisions of three Judge Bench and two Judge Bench, which have been noticed by Mohapatra, J in his judgment, including the judgment of Justice Jeevan Reddy, who was a party to the Constitution Bench in G. C. Roy, reiterating the principle that an arbitrator does not possess the power to award interest for a pre-reference period. (see Jugal Kishore, (1993) 1 SCC 114 : (1993 AIR SCW 48 : AIR 1993 SC 864), B. N. Agarwala, (1993) 1 SCC 140 : (1993 AIR SCW 3251 : AIR 1993 SC 2521) (in this case both the learned Judges, Justice Jeevan Reddy and Justice G. N. Ray were party to the Constitution Bench decision in G. C. Roy's case) and B. N. Agarwala, (1997) 2 SCC 469 : (1997 AIR SCW 824 : AIR 1997 SC 925). The arbitration proceeding has been a racket in this country and in construing the law in relation to the powers of the arbitrator, the Courts must construe the provisions of the law rather strictly. Courts would not be justified in construing the provisions and providing for something which is not there in the Act and it is in this context, I express my utter inability to construe the provisions of the Interest Act, 1839 and interpret the same to have a meaningful and purposeful object. To hold that an arbitrator possesses the power to award interest even for the pre-reference period, would tantamount to legislation in that respect and would be contrary to the well reasoned and well discussed decisions of this Court, starting from Thawardas as well as the decision of Privy Council in Bengal Nagpur Railway, which decisions though noticed in G. C. Roy's case, but have the approval of the Constitution Bench in West Punjab Factories case, though the case was not on arbitration but was of a five Judge Bench decision and possibly, it would not be proper for this Bench to take a view contrary to the same. The fact that the arbitrator has the power to deal with and decide disputes which cropped up at a point of time, would certainly not clothe the arbitrator with any power, which neither any law confers upon him nor there is any usage of trade having the force of law nor is there any agreement between the parties conferring that power. It is difficult for me to conceive that such power could be conferred upon an arbitrator for the pre-reference period on the supposition that he must be presumed to have the power to grant interest as an accessory or incidental to the sum awarded as due and payable. It is not the question of absence of any specific stipulation in the contract but the correct criteria should be whether there is a positive provision in the contract, conferring the power to the arbitrator to award interest for pre-reference period. I need not discuss any further in view of my concurrence with Brother Mohapatra, J. So, the appeals must be allowed.
(3.) D. P. MOHAPATRA, J. :- I have had the privilege of reading the draft judgment prepared by my learned brother Justice Doraiswamy Raju. He has come to the conclusion that the arbitrator appointed with or without intervention of Court, has jurisdiction to award interest on the sums found due and payable, for the pre-reference period, in the absence of any specific stipulation or prohibition in the contract to claim or grant any such interest. With respect, I am unable to agree with the said conclusion.;


Click here to view full judgement.