SUBHECHHA WELFARE SOCIETY Vs. EARTH INFRASTRUCTURE PRIVATE LIMITED
LAWS(SC)-2020-2-105
SUPREME COURT OF INDIA
Decided on February 14,2020

Subhechha Welfare Society Appellant
VERSUS
Earth Infrastructure Private Limited Respondents

JUDGEMENT

R.SUBHASH REDDY,J. - (1.)These civil appeals are filed by the complainant in Consumer Complaint Nos.1196 and 1197 of 2016, aggrieved by the order dated 06.12.2016 and the order dated 05.01.2017 in R.A.Nos.312 and 313 of 2016 passed by the National Consumer Disputes Redressal Commission (for short, 'NCDRC'), New Delhi.
(2.)The appellant-complainant is a registered Welfare Society. Consumer Complaint No.1196 of 2016 has been filed by the complainant on behalf of 8 allottees and Consumer Complaint No.1197 of 2016 has been filed by the complainant on behalf of 12 allottees with the allegations that buyers booked units with the opposite party on different dates and inspite of making major payment, possession has not been delivered to them. In the aforesaid complaint directions are sought against the opposite party to hand over possession of units in all respects or in the alternative to provide other flat of identical size or to refund the amount deposited along with interest and compensation.
(3.)It is the case of the appellant that the complainant being a society registered under Haryana Registration and Regulation Act has filed complaint on behalf of allottees, under Section 12(1)(b) of the Consumer Protection Act, 1986 (for short, 'the Act').
;