JUDGEMENT
-
(1.) These appeals by special leave arise out of an
order dated 6th June, 2002 passed by the High Court of
Andhra Pradesh whereby Writ Petitions No.9081 of 1999
and 13458 of 1993 filed by the appellant have been
dismissed and the demand for additional
charges/surcharge payable on the delayed payment of
outstanding electricity dues raised under Clause 32.2.1
and 34 of the Terms and Conditions of supply (TCS)
upheld. Facts necessary for the disposal of these
appeals may be summarised as under:
(2.) The appellant is a public limited company engaged
in the manufacture of Ferro Silicon. The industry set
up by the appellant is energy intensive in as much as it
consumes approximately 10,000 units of electricity for
every ton of Ferro Silicon produced. The appellant's
case is that the respondent-Electricity Board had
initially agreed to supply power to the appellant @ 6
paise per unit but revised the said rate to 11 paise per
unit in the year 1975. The revised rate was in the
beginning applicable only to four consumers who were
similarly situate but the number of such power intensive
consumers gradually rose to 84. On 13th December, 1983
the Board revised the general tariff but a separate
order applicable to power intensive consumers like the
appellant was issued on 29th January, 1984. Aggrieved by
the said order which permitted charging of a higher rate
of tariff, the appellant and few others filed writ
petitions before the High Court of Andhra Pradesh, which
were dismissed by a Division Bench of that Court on 3rd
April, 1985. During the pendency of the writ petition,
however, the High Court had granted an interim order of
stay against the collection of the disputed amount in
the following terms:
"There shall be stay of operation of the
order in so far as writ petition is
concerned, subject to the condition if the
writ petitioner pays at the rate of 47.89
paise per unit with effect from April 1984
onwards, furnishing Bank guarantee for the
balance to the satisfaction of the
Superintending Engineer concerned in four
weeks from today. In default of any of the
conditions, the stay stands vacated. The
bank guarantee furnished shall be renewed
for every 3 months. If the petitioner has
already paid the demand for the month of
April, on the basis of the impugned order,
this order passed by me shall be effective
from the month of May 1984 otherwise it will
be operative from April, 1984."
(3.) The dismissal of the writ petitions filed by the
appellants was assailed by them before this Court by way
of special leave petitions nos.9206-9207/1985 (C.A.
Nos.2569-2570/1985). This Court by an order dated 22nd
July, 1985 while granting leave to appeal directed
continuation of interim arrangement made by the High
Court in the following terms:
"As regards stay, after hearing learned
counsel for the parties we felt that the
order passed by the High Court dated
24.4.1984 which operated during the pendency
of the writ petitions will continue to
operate during the pendency of the appeals
with the modification that the rate of 47.89
paise per unit mentioned in the order is
rounded to 48 paise per unit.
We would, however, like to make it clear
that because of the High Court's order dated
13.4.1985, for a couple of months, there was
no such orders in regard to future payments
and the Electricity Board has received the
dues at the enhanced rates in lump sum from
some of the consumers. There will no
question of refunding the amounts back to
these consumers.
The bank guarantee already furnished by the
petitioners/appellants will be kept alive
from time to time and will cover all the
differences including the future difference.";
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.