JUDGEMENT
J.M. Panchal, J. -
(1.) By filing this Interlocutory Application, M/s. Maruti Clean Coal & Power Limited which has established a coal washery of 10 M.T.Y. capacity on Khasra Nos. 850/30, 850/24, 850/31, 850/28, 850/27 and 850/32 of Village Ratija, District Korba leased by the State of Chhattisgarh through Chhattisgarh State Industrial Development Corporation ('CSIDC' for short), has prayed to direct M/s. South Eastern Coal Field Limited ('SECL' for short) to start supply of coal immediately and issue Transit Passes/Delivery Orders through the washery of the petitioner on behalf of linked and other customers on instructions/requests from all such customers/purchasers of coal.
(2.) In order to understand the scope and ambit of the prayer made by the petitioner, it would be relevant to notice certain facts. M/s. Maruti Clean Coal & Power Limited is a company registered under the provisions of the Companies Act. It applied for the allotment of about 15 hectares (37.91 acres) of land of village Nawagaon Khurd (now Ratija), District Korba, ('the land' for short) for setting up a Coal Beneficiation Plant with a capacity to wash 10 million tons of coal per annum. The land demanded was adjacent to already existing two coal washeries one of which was set up by ST-CLI in which one Aryan Coal Beneficiation Pvt. Ltd. has 26% holdings and another Coal Washery set up belongs to Aryan itself. The officials of the Revenue, Forest and Industry Departments of the State conducted a thorough inspection of the land demanded by the petitioner. After being satisfied that the land demanded was not forest land and requirements of environmental laws were complied with by the petitioner, the officials recommended to the State to allot the land to the petitioner. Pursuant to the said recommendation, a lease deed dated December 5, 2002 for a period of 99 years was executed in favour of the petitioner by the State of Chhattisgarh through CSIDC. The purpose for which the lease deed was executed was to enable the petitioner to set up a coal washery. Pursuant to the said lease deed, the petitioner was put in possession of the land. However, subsequently, SECL claimed title to the land and alleged that the land did not belong to the State Government and, therefore, could not have been leased by the State to the petitioner.
In March/April 2003, one Mr. B.L. Wadhera, a public spirited citizen instituted WP (C) No. 1264/2003 before the High Court of Chhattisgarh at Bilaspur to prevent the petitioner from setting up its coal washery on the land allotted to it by the State Government on the ground that the land allotted were forest land. The High Court, by an ex parte order dated April 24, 2003, directed the petitioner to maintain status quo regarding the land allotted to it and not to cut trees standing on the land till further orders. In view of the dispute pertaining to the title of the land between SECL and the State Government, the Union of India, vide letter dated May 7, 2003 sent through the Ministry of Coal, gave the petitioner two options (1) to wait until title issue is decided; or (2) to proceed on the assumption that the title vests in SECL and on that basis, to request the SECL to allot the land to the petitioner. It was also mentioned in the said letter that in the event the petitioner chose the second option, Coal India Limited and SECL would be requested by the Ministry to initiate action for leasing the land to the petitioner. The record shows that by letter dated May 9, 2003, the petitioner elected the second option. The petitioner filed an application for vacation of the stay order. The High Court, by order dated May 9, 2003, modified its earlier order and allowed the petitioner to continue with the construction of the main building but restrained it from installing the machineries. Meanwhile, the SECL wrote a letter dated June 27, 2003 to the Ministry of Coal stating that it had no objection in leasing the land to the petitioner subject to certain conditions including the condition that the fact that the land belonged and belongs to SECL is acceptable to the petitioner. Feeling aggrieved by order dated May 9, 2003, Mr. B.L. Wadhera filed SLP (C) No. 22531 of 2003. This Court, by order dated November 24, 2003 stayed further construction on the land. Subsequently, the said SLP was tagged with IA No. 857-858 of 2003 filed by Mr. Wadhera and one Mr. Deepak Aggarwal respectively. This Court, by judgment dated April 10, 2006 in case of T.N. Godavarman Thirumulpad v. Union of India and Ors. (2006) 5 SCC 28 dismissed the application of Mr. Deepak Aggarwal observing that it was filed with mala fide intention. The interim order passed staying further construction was vacated. On the pronouncement of judgment by this Court, the petitioner filed an application in the writ petition pending before the High Court of Chhattisgarh with a prayer to dismiss the writ petition. The record shows that the said application was heard with two other connected petitions and judgment was reserved. However, the judgment could not be pronounced by the High Court. Therefore, the petitioner filed an application for vacating the interim orders dated April 23, 2003 and May 9, 2003. Listing of the said application was refused by the Registry on the ground that in the main matter, judgment was reserved. Meanwhile, the petitioner completed construction of the main building. The order for purchase of machineries to be installed was already placed.
(3.) On December 9, 2004, SECL filed Civil Suit No. 90-A of 2004 against the State of Chhattisgarh and the petitioner contending, inter alia, that the land allotted to the petitioner company by the State of Chhattisgarh through CSIDC had vested in SECL and that SECL is the owner and in possession of the land in question. Various other litigations and proceedings were initiated by several parties pertaining to the land allotted to the petitioner company. The Ministry of Coal, by letter dated December 30, 2005 advised SECL to implement the instructions dated May 7, 2003 mentioned in para (b). The petitioner thereupon addressed a letter dated June 14, 2006 to SECL to inform the petitioner about the lease premium/rent to be deposited. The record of the case further shows that in spite of instructions issued by the Ministry of Coal and request made by the petitioner, SECL did not initiate steps for leasing the land to the petitioner. Therefore, the petitioner has filed Special Leave Petition No. 20238 of 2006 challenging validity of order dated April 24, 2003 as modified by order dated May 9, 2003 in WP No. 1264 of 2003 pending before the High Court of Chhattisgarh. In the abovereferred special leave petition, the Court has issued notice and the said SLP is pending for final disposal. Thereupon, the petitioner company filed Transfer Petition No. 53 of 2007 in this Court to direct that all the connected matters including the suit, writ petitions and/or appeals be heard together and transferred to the High Court of Chhattisgarh at Bilaspur. The said Transfer Petition was allowed. Pursuant to the directions given by this Court, the number of Civil Suit was changed from 90-A of 2004 to Civil Suit No. 1-A of 2008. The said suit and all other connected writ petitions, appeals etc. are pending adjudication before the High Court of Chhattisgarh at Bilaspur.;