JUDGEMENT
-
(1.) Leave granted. Heard.
(2.) The appellant (State of Himachal Pradesh represented by the
Executive Engineer, I&PH Division, Hamirpur) entered into a contract with
the respondent on 15.7.2002, for the construction of a water purification
plant. The respondent raised a dispute in regard to the payment for extra
work, which was referred to arbitration. The arbitrator made an award dated
5.11.2007 in favour of the respondent and sent it to the parties by speed post.
The postal cover containing the award was received by a peon/beldar in the
office of the Executive Engineer on 10.11.2007 (a Saturday) which was a
government holiday. 11th November, 2007 being a Sunday was also a
holiday. It was received by the Executive Engineer on 12.11.2007.
(3.) A petition under section 34 of the Arbitration and Conciliation Act,
1996 ('Act' for short) was filed by the appellant on 11.3.2008, challenging
the arbitral award. The petition was accompanied by an application under
sub-section (3) of section 34 of the Act, for condonation of delay of 28 days
in filing the petition. The respondent resisted the application contending that
the petition under section 34 was filed beyond the period of 3 months plus
30 days and therefore, was liable to be rejected. A learned Single Judge of
the High Court dismissed the application for condonation of delay and as a
consequence dismissed the petition under section 34 of the Act. He held that
as the award was received in the office on 10.11.2007, the period of three
months, that is "90 days" had to be reckoned from 11.11.2007 by excluding
the date of receipt; that the said three months period ended on 9.2.2008; that
even if the maximum additional period of 30 days was counted thereafter
(by calculating from 10.2.2008), the last date of limitation for filing the
petition would have been 10.3.2008 and therefore the petition filed on
11.3.2008 was barred by limitation. He held that court had power to condone
the delay only to a maximum period of ninety days plus thirty days and
therefore, the delay in filing the petition on 11.3.2008 could not be
condoned. Feeling aggrieved the appellant has filed this appeal by special
leave.;