LAWS(SC)-2010-4-12

STATE OF MAHARASHTRA Vs. HINDUSTAN CONSTRUCTION COMPANY LTD

Decided On April 01, 2010
STATE OF MAHARASHTRA Appellant
V/S
HINDUSTAN CONSTRUCTION COMPANY LTD. Respondents

JUDGEMENT

(1.) Leave granted.

(2.) The question presented in this appeal by special leave is : whether in an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (for short '1996 Act') from an order refusing to set aside the award, an amendment in the memorandum of appeal to raise additional/new grounds can be permitted.

(3.) M/s. Hindustan Construction Company Limited (respondent) and the State of Maharashtra (Irrigation Department, the Executive Engineer - appellant) entered into a contract on March 14, 1992 being ICB Contract No. II/1992 for the construction of civil work of Pressure Shafts and Power House Complex at Koyana Hydro Electric Project, Stage-IV. The contract work was completed by respondent within the extended period i.e., by March 31, 2000. However, it appears that disputes arose between the parties in respect of the work carried out by respondent in relation to (a) revision of percentages for hidden expenses, over breaks and profit for further additional cases of extract items/rate revision; (b) claim for extended stay at site; (c) revision of rate for Pressure Shaft excavation; (d) fixation of new rate on account of variation in the item of Transformer hall arch concrete; and (e) fixation of new rate on account of variation in the item of Transformer Hall excavation. These disputes were referred to the Arbitral Tribunal. The Arbitral Tribunal made award on June 26, 2003 and a signed copy thereof was forwarded to the appellant along with the letter dated June 30, 2003. By the said award the Arbitral Tribunal awarded an amount of Rs. 17,81,25,152/- to respondent and further directed that if the said amount was not paid by appellant within two months from the date of the award, then the awarded sum shall carry an interest at the rate of 15 per cent per annum from June 27, 2003.