JUDGEMENT
Norman Macleod, C J -
(1.)The plaintiffs filed this suit against the defendants to recover damages for the breach of a contract, dated the 9th May 1918, whereby the defendants agreed to sell to the plaintiffs and the plaintiffs agreed to buy from the defendants 50 tons of Yellow Katha wheat at Rs. 8-2-0 per cwt. on the terms and conditions mentioned in the contract. Delivery was to be May-June 1-918 at the sellers option. Therefore the last day for delivery was the 30th day of June 1918. The railway receipts relating to the contract goods were handed over to the plaintiffs within the contract time. The plaintiffs took delivery and warehoused the goods about the 13th of July 1918. Thereafter on examining the goods the plaintiffs were dissatisfied with their quality and contended that they were not a proper and fair tender against the contract. Eventually a survey was held and the plaintiffs rejected the goods. The plaintiffs, on the 23rd of August 1918, bought 49 tons of wheat of the quality and description mentioned in the contract and they claim to recover the difference between what they paid for these 49 tons and the contract price. They also claim interest on the amount awarded.
(2.)The learned trial Judge found that there had been a breach of the contract and considered the question whether the date of the breach was the 1st of July 1918 or the date when the parties actually found that the goods tendered were not of the contract quality, and came to the conclusion that where there was an attempted performance of the contract the date of the breach must be taken as of the date when the parties actually found that the goods tendered were not of the contract quality. He found that there was no delay on plaintiffs part to buy against the sellers, and he passed a decree in favour of the plaintiffs for Rs. 2250-150. The learned Judge also seems to have allowed interest on the amount which the plaintiffs had paid for the goods from the date that the money was paid until it was returned by the defendants.
(3.)This is an ordinary case of breach of contract to deliver goods which were contracted for to be delivered at a future date. The general rule is that if there is a breach of the contract, the measure of damages is the difference between the contract rate and the market rate at the date of the breach. The date of the breach must be considered as that date when the seller ought to have tendered goods of the contract quality and failed., to do so. It must follow that if the buyer is dissatisfied with the quality of the goods tendered and demands a survey, some time must elapse before a survey is held and a decision is given as to the quality of the goods; but that does not postpone the date of the breach. It must be the due date unless the parties come to an agreement that the due date shall be postponed until it is ascertained whether the goods are of the contract quality or not. In this case there is no evidence whatever of any such agreement. The ordinary course of events followed after the buyers claimed to reject the goods on the ground that the goods tendered were not of the contract quality. The plaintiffs have failed to prove that the due date must not be taken to be the date of the breach and they have not proved that there was any difference between the contract rate and the market value at the due date. Therefore, they failed to prove that they suffered any damage owing to the goods not being of the contract quality.
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.