SHAILESH KUMAR SINHA Vs. STATE OF BIHAR
LAWS(PAT)-2021-1-21
HIGH COURT OF PATNA
Decided on January 04,2021

SHAILESH KUMAR SINHA Appellant
VERSUS
STATE OF BIHAR Respondents

JUDGEMENT

RAJEEV RANJAN PRASAD,J. - (1.) Heard learned counsel for the petitioner and learned counsel for the State. Petitioner has prayed for the following reliefs: - "(I) For issuance of an appropriate order/orders direction/directions writ in the nature of mandamus directing the commanding to the Respondents to release the Mahindra Scorpio Motor Car vide Registration No. BR-01PK-1102, Chassis No. MA1TA2TDKK2A18679, Engine No. TDK4A80389 of petitioner which has been seized by the police Patna in connection with P.R. No. B-66 of 2020 dated 13.11.2020 offence under section 30(a), 32(1), 32(3), 41(1), 41(2) Bihar Prohibition and Excise (Amendment) Act, 2018. (II) And further be pleased to grant other relief/reliefs as the petitioner is entitled for."
(2.) Learned counsel for the petitioner prays that the petition be disposed of in terms of the judgment dated 22.12.2020, passed in Civil Writ Jurisdiction Case No.9592 of 2020 (Dharmendra Mahto versus The State of Bihar).
(3.) In the case of Dharmendra Mahto (supra) this Court has referred and discussed all the previous case laws on the subject. Some of the judgments rendered in similar matters are as under:- (i) Md. Shaukat Ali Vs. The State of Bihar and Ors.,2020 3 PLJR 927. (ii) Umesh Sah Versus The State of Bihar and Ors.,2020 3 PLJR 931. (iii) Bunilal Sah @ Munilal Sah Vs. The State of Bihar and Ors.,2020 3 PLJR 935. The operating part of the judgment in the case of Md. Shaukat Ali are being briefly reproduced as under:- "(a) Since the vehicle in question stands seized in relation to the FIR which stood registered long ago, in case confiscation proceeding has not been initiated, it must be initiated within a period of 15 days from today and that confiscation proceeding stands initiated, we direct the appropriate authority under the Act to forthwith ensure that such proceedings be concluded not later than 30 days. (b) The petitioner undertakes to make himself available in the office of the concerned appropriate authority empowered under Section 58 of the Act i.e. District Collector, in his/her office on 24.01.2020 at 10:30 A.M. (c) We further direct the appropriate authority to positively conclude the confiscation proceeding within next thirty days on appearance of the petitioner. If for whatever reason, such proceeding cannot be concluded, in that event it shall be open for the authority to take such measures, as are permissible in law, for release of the vehicle in question by way of interim measure, on such terms as may be deemed appropriate, considering the attending facts and circumstances of the case. (d) If eventually, the appropriate authority arrives at a conclusion that the property is not liable to be confiscated, it shall be open for the petitioner to seek damages in accordance with law and have appropriate proceedings initiated against the erring officials/officers. Learned counsel for the petitioner states that the certified copy of the order shall be made available to the concerned District Collector on the date so fixed. For future guidance, where parties have not approached this Court, we issue the following direction:- The expression "reasonable delay" used in Section 58 of Chapter VI of the Act, in our considered view, necessarily has to be within a reasonable time and with dispatch, which period, in our considered view, three months time is sufficient enough for any authority to adjudicate any issue, more so, when we are dealing with confiscatory proceedings." ;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.