CONTINENTAL CONSTRUCTION COMPANY Vs. BOARD OF TRUSTEES VISAKHAPATNAM PORT TRUST
LAWS(APH)-2008-2-90
HIGH COURT OF ANDHRA PRADESH
Decided on February 02,2008

CONTINENTAL CONSTRUCTION COMPANY Appellant
VERSUS
BOARD OF TRUSTEES VISAKHAPATNAM PORT TRUST. Respondents

JUDGEMENT

- (1.) THIS Civil Miscellaneous Appeal is filed under section 39 of the Indian arbitration Act, 1940 questioning the order dated 5. 1. 2000 passed in O. P. No. 14 of 1990 on the file of Ist Additional Senior Civil Judge, Visakhapatnam, whereby and where under the learned Additional Senior Civil Judge allowed the application filed under section 30 of the Indian Arbitration Act, 1940 and set aside the award dated 25. 9. 1989 and directed the appellant herein to pay seigniorages fee and cess amounting to Rs. 27,84,617. 10 together with interest @ 12 percent from 23. 6. 1988.
(2.) BACK ground facts of the case, in brief, are : Visakhapatnam Port Trust (hereinafter referred to as Claimant) invited tenders for execution of C2 and C3 contract works. They are land based works at lova Gardens, and Marine Works and break water construction. Continental construction Company (hereinafter referred to as the Contractor) submitted tender and the same came to be accepted after due negotiations. The letter of intent for both C2 and C3 contracts were issued on 7. 5. 1971 and agreements were entered into between the parties. The contractor was permitted to use the quarries of the claimant and the claimant agreed to pay value of sized rocks. The contractor agreed to pay royalty to the claimant @ Rs. 2. 50/- per 100 cft. However, royalty was to be paid only on quantity of rock actually used on works. While quarrying operations were in progress, demand notices came to be issued by district Revenue Officer under A. P. Minor, Mineral Concessions Rules demanding seigniorage fee. District Collector, Visakhapatnam attached the dumpers of the contractor. Thereupon, the contractor filed W. P. No. 3386 of 1974. The said writ petition came to be allowed on 9. 12. 1974 directing the District Collector to issue appropriate notice to the claimant and the contractor. Accordingly, notices came to be issued to the contractor and the claimant. Ultimately, liability to pay seigniorage fee came to be fastened on the claimant by the department of Mines and Geology vide proceedings No. 2195/s1/75 dated 14. 9. 1978 of the Director of Mines and Geology, Hyderabad.
(3.) THE claimant filed W. P. No. 4940 of 1978 assailing the order of the director of Mines and Geology as confirmed by Government of A. P. The said writ petition came to be allowed in part setting aside the penalty and giving liberty to the claimant to recover seigniorage fee if it is permissible according to law. For better appreciation, we may refer the relevant portion of the order and it is thus: " It is well settled that levy of penalty is not automatic nor is the levy at ten times obligatory. It depends upon the facts of a given case. The collector himself had informed the petitioner on an earlier occasion that no such permission is required. The petitioner bona fide believed in the said representation, and did not think it necessary to apply for permission for the said quarrying. There was also some ambiguity about the language of the proviso to Rule 5 (1 ). In all the circumstances, the levy of penalty, in our opinion, is totally unwarranted and uncalled for. After all, the petitioner is a public sector concern, and it cannot be believed that it carried on quarrying operations inspite of knowing that it is illegal. Not that we are saying that such knowledge is necessary. What is important is the letter of the Collector dated 28. 2. 1970, which clearly told the petitioner that such permission is not necessary. In these circumstances, the levy of penalty must be held to be bad. The writ petition is, accordingly, allowed in part, and the levy of penalty in a sum of Rs. 2,03,25,672. 90 ps. , is quashed. The rest of the demand shall, however, stand undisturbed. There shall be no order as to costs. So far as the question as to who is liable to pay the said fee is concerned, it is a matter between the petitioner and the contractor. The contractor is not represented before us. Without hearing him it is not possible for us to express any opinion on the said question. We, therefore, decline to express any opinion on this question. If, however, the petitioner thinks that it is entitled to recover the said amount of fee or cess from the contractor, it is open to it to adopt such remedies as are open to it according to law. ";


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.