JUDGEMENT
P.VENKATRAMA REDDY, J. -
(1.) This
appeal under Sec. 39 of the Arbitration Act,
arises outoftheorderpassed by the Additional
subordinate Judge, Ongole, in O.P.No: 60 of
1990. This O.P. was filed by the respondent
herein who was entrusted with the contract
work for the construction of Kalyanamandapam
at Ongole for the appellants viz., Tirumala
Tirupathi Devasthanam. The work was
commenced under an Agreement, dated
6.11.1985 (Ex B-1). It appears that some
disputes arose as regards the execution of the
work and the payments due to the respondent.
These disputes related to imposition of certain
fines and recoveries made from the contractor
and also as regards the defective execution of
work by the contractor.
(2.) On23.6.1989,i.e., some time after the
construction was completed, the respondent-contractor submitted a letter requesting the
Executive engineer (third appellant herein),
to release the final bill amount after reducing
the rates for the three deficient items of
work carried out by him. This is marked as
Ex. B-4 in the said O.P. A few days thereafter
i.e., on 29.6.1989, the appellants finalised
the amounts due to the respondent and paid
the money after the respondent endorsed on
'M-Book' that he had no objection for the
measurements, rates and the amounts
mentioned in the final bill and he was
agreeable for the same. This is marked as
Ex. B-3 in the O.P.
(3.) Some time after receiving the payment,
the respondent notified his objections for the
amounts paid to him under the final bill. It is not
clear from the record whether the respondent
sought for appointment of anarbitrator to resolve
thedisputes. But, on25.6.1990, the respondent
filed the O.P. under sec. 20 of the Arbitration
Act with a prayer to direct the appellants here in to
file the original agreement No: 45 CE/1985-86
and to appoint a retired chief Engineer as a
sole arbitrator and to refer the disputes and
differences for his adjudication. In the petition
the respondent made a reference to
"outstanding claims" and he mentioned 14
claims. Some of them relate to the alleged
execution of certain supplemental items not
provided for by the agreement for which extra
payment was claimed. The respondents in the
O.P. (the appellants herein) objected to the
reference mainly on the ground that there is no
arbitrable dispute in view of the categorical no-claim endorsement made by the contractor
while receiving the final bill amount on 29.6.1989.
The learned Addl. Subordinate Judge observed
that there is a dispute regarding the circumstances
under which the respondent-contractor
executed exhibits B-3 and B-4and that dispute
including all the claims has to be resolved by an
arbitrator.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.